Dismantling, packing, and loading for transport to Portugal, Tunisia, and Mexico. Completed by 16 technicians in two months, within the planned timeframe.
4.8 Bestbewerteter
Service 2026verifiziert von: TrustindexTrustindex überprüft, ob das Unternehmen auf Grundlage der in den letzten 12 Monaten auf Google gesammelten Bewertungen einen Bewertungswert über 4.5 aufweist und sich damit für den Erhalt des Top-Rated-Zertifikats qualifiziert.






























Organization of all lifting equipment for transporting people and building components at the start of the project.
Professional dismantling of five injection molding systems consisting of injection molding machines, robots, and hydraulic presses.
Components weighing up to 40 metric tons are moved out of the warehouse using two pick-and-carry cranes; smaller components are moved using a 12-metric-ton forklift.
Disassembly and packaging of six measuring machines in collaboration with the manufacturer’s team and in accordance with the manufacturer’s specifications.
Packaging of all plant components in a manner suitable for transport and loading onto transport vehicles.
Environmentally sound disposal of 850 liters of hydraulic oil and oil-contaminated equipment.