FAT and SAT are the two crucial tests that must be completed before a new or retrofitted system goes into production. During the Factory Acceptance Test, the system is accepted at the manufacturer’s plant; during the Site Acceptance Test, it is accepted at its future location. Between these two acceptance tests, the system must be dismantled, transported, and reassembled. It is precisely during this process that many deviations arise, which delay the SAT and postpone the start of production. We’ll show you the procedure for both tests, what mistakes you should avoid, and how to properly prepare for FAT and SAT.
What Do FAT and SAT Mean?
Factory Acceptance Test: Acceptance Testing at the Manufacturer’s Facility
The Factory Acceptance Test (FAT) takes place before the system leaves the manufacturer’s facility. The client and the manufacturer jointly verify whether the mechanical, electrical, and control systems meet the agreed-upon requirements. Since the actual production environment is not present, test materials or simulated signals are often used.
Site Acceptance Test: the on-site acceptance test
The Site Acceptance Test (SAT) is conducted after the system has been installed and commissioned at the site. What matters now is how the system interacts with the real-world environment: media supply, network, upstream and downstream systems, and actual products. Only a successful SAT demonstrates that the system operates reliably under production conditions.
FAT and SAT Compared
Both tests complement each other. The FAT identifies defects early on, while they can still be corrected with minimal effort at the manufacturer’s plant. The SAT confirms that the system functions in its actual environment after transport and installation. The key differences:
- Location: FAT at the manufacturer’s facility, SAT at the operator’s site
- Timing: FAT before delivery; SAT after installation and commissioning
- Conditions: FAT uses test materials and simulation; SAT uses real media, products, and interfaces
- Purpose: FAT tests the system itself; SAT tests the system within the overall system
A passed FAT therefore does not replace a SAT. Conversely, a thorough FAT saves a lot of time on-site because fewer errors are discovered only once the system is installed.
Why Acceptance Is So Important in a Contract
In many projects, acceptance has tangible consequences. Payment milestones, the transfer of responsibility to the client, or the start of the warranty period often depend on it. The contract specifies which consequences apply in each individual case. Therefore, acceptance criteria, the scope of testing, and the handling of remaining defects should be clearly defined in the specifications and the contract. Structured
project management in industrial assembly ensures that these points are not left to be discussed only at the time of acceptance.
Procedure for a Factory Acceptance Test
A FAT follows a pre-agreed test plan. Typical steps include:
- Define the test plan and criteria: Which functions, performance values, and tolerances will be tested, and what constitutes a pass?
- Review documentation: Circuit diagrams, bills of materials, software versions, and documentation are checked for completeness.
- Visual and mechanical inspection: Workmanship, labeling, accessibility, and safety guards are assessed.
- Test electrical and control systems: Signals, safety functions, and operating procedures are tested. This requires in-depth expertise in electrical engineering and automation.
- Conducting performance tests: The system is run with test material under conditions that are as realistic as possible.
- Prepare a report: Results, deviations, and defects are documented along with the responsible parties and deadlines.
Between FAT and SAT: Dismantling, Transport, and Reassembly
After the FAT, the system has been tested. To ensure it arrives in the same condition for the SAT, every step in between must be carefully planned.
Labeling and Documentation During Dismantling
Cables, assemblies, interfaces, and settings are clearly labeled and documented before disassembly. This ensures that the system can be reassembled at its destination in exactly the same condition as it was during the FAT.
Packaging and Transport
Sensitive components require protection against vibration, moisture, and corrosion. Overseas shipments also involve long periods of inactivity and changes in climate. We describe what matters most in this regard in our articles on
machine transport and
international machine relocations.
Reassembly, Alignment, and Connection
Commissioning as Preparation for the SAT
The SAT is preceded by the
commissioning of industrial plants. Functions are tested step by step and parameters are adjusted until the plant is operating stably. Any deviation from the condition observed during the FAT should be identified before on-site acceptance testing begins.
Procedure for a Site Acceptance Test
The SAT builds on the results of the FAT and supplements them with the actual conditions at the site:
- Checking the infrastructure: foundation, power supply, compressed air, cooling, and network
- Functional and safety testing: all functions and safety devices in a real-world environment
- Trial operation: Production using actual material over an agreed-upon period, including performance verification
- Orientation: Training for operating and maintenance personnel
- Acceptance report: Results, outstanding items with deadlines, and formal approval
Common Errors in FAT and SAT
- Unclear Acceptance Criteria: Without measurable criteria, every acceptance becomes a matter of negotiation.
- Unrealistic FAT: Tests that have nothing to do with subsequent operation shift errors to the construction site.
- Lack of documentation during disassembly: Without labeling, reassembly takes time and creates potential sources of error.
- Infrastructure not ready: Missing connections or a foundation that hasn’t fully cured block the SAT.
- Inadequate staffing: Without experts from production, maintenance, and electrical engineering, defects go undetected.
- Defects with no one responsible: Outstanding issues require deadlines and clear accountability.
Checklist: How to Prepare for FAT and SAT
- Acceptance criteria and scope of testing specified in the contract
- Test plan for FAT and SAT agreed upon with all parties involved
- Participants designated for both dates
- Documentation and software version complete prior to the FAT
- Labeling and disassembly plan prepared
- Packaging and transportation coordinated with the facility
- Infrastructure at the site of operation completed on time
- Test material provided on-site for trial operation
- Template for the acceptance report created
Installation, relocation, and commissioning with A & P Industriemontage
Since 2004, we have been assisting industrial companies with the installation, relocation, and commissioning of machinery and equipment. Our focus is precisely where the greatest risks arise between FAT and SAT: disassembly and labeling, transport preparation, reassembly, alignment, electrical installation, and support during startup.
Our team of assemblers, metalworkers, welders, electronics technicians, and mechatronics engineers works in an interdisciplinary manner. A dedicated contact person will guide your project from planning through to acceptance, whether in Germany, Europe, or worldwide—for example, in the U.S., Mexico, China, India, or South Africa. Learn more about our services under
“Machinery and Plant Installation ” and
“Machinery Relocation.”
Planning FAT and SAT as a Continuous Process
FAT and SAT are not two separate milestones, but rather the beginning and end of a continuous process. By establishing clear criteria, thoroughly documenting the disassembly, and carefully planning the reassembly, you can reach the SAT without any surprises and start production on schedule. Are you planning a plant relocation or a commissioning with acceptance? Contact us.